Johannesburg Water Current Projects Listed below;

 

Project nameService ProviderContract Number% Completion
NWWTW Unit 4 - liqourJW1359986%
Ennerdale WWTW: Infrastructure Renewal Plan - Module mixersJW1422697%
Unit 5 -Phase 2 (Civil works)JW13896RR60%
NWWTW IRP Phase 1 Electrical MV Upgrade and RefurbishmentJW1405494%
Randburg depot - Completion of the contruction of new Randburg DeptJW1426686%
Alternative Energy Project Phase 1JW1441295%
Woodmead Reservoir JW1428912%
Erand Tower- Construction of New 2.0 Ml Tower and PumpstationJW13570RRRRR37%
Florida North pump stationJW13829RR99%
Kibler Park Sewer Pumpstation UpgradeJWOPS032/2232%
Refurbishment of Hector Norris Pump Station including pumps, VSDs, PLC and associated electrical worksJW1428753%
Pressure Management Phase 2B: Soweto PRVsJW1409690%
Pressure Management Phase 2A: Soweto PRVsJW1409580%
T-CODESOM2020_JW OPS 049/19R100%
Stretford Ext 6, 7 and 8 Sewer Bulk Pipe ReplacementJW14228B69%
Stretford Ext 7 Sewer Pipe Replacement Phase 2JW14228C40%
Stretford ext 4 Outfall SewerJW1429043%
Provision of basic water in CrosbyJW1441699%
Alexandra Renewal of Secondary Mains and Discretisation in Sub Block CUFW913_BLK C97%
Alexandra Renewal of Secondary Mains and Discretisation in Sub Block DUFW913_BLK D99%
Orange Farm 2BJW1385899%
Anthea Nancefield outfall SewerJW13575 RRR40%
Halfway House Water UpgradeJW143240%
Blairgowrie Water Pipe Replcament Phase 1JW14220H99%
Diepsloot Sewer BridgesJW13518RR24%
Construction of a 26ML Concrete Reservoir and a 2ML Water Tower in Brixton with
associated pipe and pump works
JW1432259%
Protea South Ext 9 Sewer Pipe Replacement Phase 9JW1437690%
Sewer Pipe Replacement Louis Botha 3JW1423198%
Sewer Pipe Replacement Louis Botha 1JW1422996%
Parkwood Phase 3 Sewer Pipe ReplacementJW14228A27%
Cedar Lakes Sewer Pipe ReplacementJW1437799%
Sharonlea Water Pipe Replacement Phase 2JW14220B98%
Sharonlea Water Pipe Replacement Phase 1JW14220A98%
STS Meters Supply and technical supportJW14329_C100%
STS Meters Supply and technical supportJW14329_A100%
STS Meters Supply and technical supportJW14329_B100%
Supply and intsallation of STS water meters in cosmo city Phase 2JW143355%
NWWTW Unit 4 - liqour86%
Ennerdale WWTW: Infrastructure Renewal Plan - Module mixers97%
Unit 5 -Phase 2 (Civil works)60%
NWWTW IRP Phase 1 Electrical MV Upgrade and Refurbishment94%
Randburg depot - Completion of the contruction of new Randburg Dept86%
Alternative Energy Project Phase 195%
Erand Tower- Construction of New 2.0 Ml Tower and Pumpstation37%
Florida North pump station99%
Kibler Park Sewer Pumpstation Upgrade32%
Refurbishment of Hector Norris Pump Station including pumps, VSDs, PLC and associated electrical works53%
Pressure Management Phase 2B: Soweto PRVs90%
Pressure Management Phase 2A: Soweto PRVs80%
T-CODES100%
Stretford Ext 6, 7 and 8 Sewer Bulk Pipe Replacement69%
Stretford Ext 7 Sewer Pipe Replacement Phase 240%
Stretford ext 4 Outfall Sewer43%
Provision of basic water in Crosby99%
Alexandra Renewal of Secondary Mains and Discretisation in Sub Block C97%
Alexandra Renewal of Secondary Mains and Discretisation in Sub Block D99%
Orange Farm 2B99%
Anthea Nancefield outfall Sewer40%
Blairgowrie Water Pipe Replcament Phase 199%
Diepsloot Sewer Bridges24%
Construction of a 26ML Concrete Reservoir and a 2ML Water Tower in Brixton with
associated pipe and pump works
59%
Protea South Ext 9 Sewer Pipe Replacement Phase 990%
Sewer Pipe Replacement Louis Botha 398%
Sewer Pipe Replacement Louis Botha 196%
Parkwood Phase 3 Sewer Pipe Replacement27%
Cedar Lakes Sewer Pipe Replacement99%
Sharonlea Water Pipe Replacement Phase 298%
Sharonlea Water Pipe Replacement Phase 198%
STS Meters Supply and technical support100%
Supply and intsallation of STS water meters in cosmo city Phase 25%
Orlando West 7B100%
Orange Farm 2A100%
Gemsbok Water Pipe Replacement Phase 1100%
Gemsbok Water Pipe Replacement Phase 2100%
Orange Farm 2C100%
Goudkoppies WWTW infrastructure renewal planEigenbau Dzenga Projects JV100%
ArmadaleMaletebego80%
Gallo Manor ext 3Planet Earth Constructions cc90%
Glenvista ext 4 phase 1Paba Kevcon90%
Glenvista ext 4 phase 2Matshelane Trading cc90%
Discovery Ext. 9DKPB Construction80%
Douglasdale Ext. 4Planet Earth Constructions cc80%
Ferndale Ext. 3 Phase 1Thamandla Construction and Maintenance45%
Ferndale Ext. 3 Phase 2Thamandla Construction and Maintenance49%
Ferndale Ext. 3 Phase 3Matshelane Trading cc90%
Forest Town Phase 1Abram Mashego Construction Puno Harvest JV90%
Forest Town Phase 2Iviwe Mosobotlhale JV90%
Forest Town Phase 3Athivhonali Trading and Projects cc Muthash Jv95%
Forest Town Phase 4Athivhonali Trading and Projects cc Muthash Jv95%
Industria West Phase 1Iviwe Mosobotlhale JV92%
Industria West Phase 2Nandipha’s Projects cc96%
Industria West Phase 3Maletebogo Business Enterprise96%
KellandXono Civil Enterprises/Umakho JV85%
Kengies AH Phase 1Mavu-Ashu Civil Constructions cc85%
Kengies AH Phase 2Athivhonali Trading and Projects cc Muthash Jv100%
LongdaleDKPB Construction90%
Lyme ParkNandipha’s Projects cc95%
Booysens Phase 1TML Civils  Pty Ltd92%
Booysens Phase 2DKPB Construction89%
Booysens Phase 3McBEE Trading93%
Booysens Reserve Phase 1Matshelane Trading cc90%
Booysens Reserve Phase 2A and P Civils and Trading (Pty) Ltd60%
Glenvista Ext. 4 Phase 3Thamandla Construction and Maintenance60%
Gold Reef OphitonAdicon Investments (Pty) Ltd90%
Gold Reef ReuvenA and P Civils and Trading (Pty) Ltd80%
Gold Reef SpringfieldAdicon Investments (Pty) Ltd90%
Hursthill Phase 1Phumelela Dlomo Construction75%
Hursthill Phase 2Xono Civil Enterprises/Umakho JV95%
Hursthill Phase 3Nandipha’s Projects cc95%
Selby Phase 1Boxani Building And Civil65%
Selby Phase 2Phumelela Dlomo Construction70%
Wemmer Phase 1TML Civils  Pty Ltd80%
Wemmer Phase 2Abram Mashego Construction Puno Harvest JV90%
Wemmer Phase 3Little Rocky Development Projects85%
Green Side Water Pipe replacement - Vukuphile Phase 2AMQME Business Enterprise100%
Green Side Water Pipe replacement - Vukuphile Phase 2AMQME Business Enterprise100%
Green Side Water Pipe replacement - Vukuphile Phase 2AMaziya Gembe Development100%
Green Side Water Pipe replacement - Vukuphile Phase 2ALetsemeng Civil Works100%
Green Side Water Pipe replacement - Vukuphile Phase 2AThabong Group (Pty) Ltd100%
Green Side Water Pipe replacement - Vukuphile Phase 2A100%
Green Side Water Pipe replacement - Vukuphile Phase 2AEdawonga Trading and Projects 2A100%
Green Side Water Pipe replacement - Vukuphile Phase 2AMadings Business Enterprise100%
Green Side Water Pipe replacement - Vukuphile Phase 2ALaggy Business Enterprise100%
Green Side Water Pipe replacement - Vukuphile Phase 2ASabuh Trading100%
Green Side Water Pipe replacement - Vukuphile Phase 2AThabong Group (Pty) Ltd100%
Green Side Water Pipe replacement - Vukuphile Phase 2ANgqola and Dlamini at last90%
Green Side Water Pipe replacement - Vukuphile Phase 2ABuyambo Investment Enterprise cc85%
Cosmo City Sewer ReplacementThamandla Construction66%
Louis Botha Sewer ReplacementThalami Civils
ZANDSPRUIT 6Motla Projects cc10%
ZANDSPRUIT 1F & A Civils cc45%
ZANDSPRUIT 2Little Rocky Development Projects65%
ZANDSPRUIT 3MC BEE Trading cc65%
ZANDSPRUIT 4Planet Earth Construction cc18%
ZANDSPRUIT 5Maletebogo Toro ya Bakwena25%
Orange Farm ext 1 Sewer pipe replacement Phase 1Motla Projects5%
Orange Farm ext 1 Sewer pipe replacement Phase 2Thalami Civils5%
Allen's Nek Sewer Pipe ReplacementPlanet Earth Construction15%
Bellevue Sewer Pipe Replacement Phase 1Planet Earth Construction20%
Strubensvalley Sewer Replacement Phase 1Limontha80%
Bellevue Sewer Pipe Replacement Phase 2Motla Projects38%
Bellevue Sewer Pipe Replacement Phase 3TML Civils81%
Bellevue Sewer Pipe Replacement Phase 4Maletebogo Business Enterprise86%
Bellevue Sewer Pipe Replacement Phase 5Mavu Ashu Construction37%
Doornfontein Sewer Replacement Phase 1Planet Earth Construction20%
Doornfontein Sewer Replacement Phase 2Isizwe Construction50%
Dunkeld West Phase 1 Sewer UpgradeMotla Projects10%
Dunkeld West Phase 2 Sewer UpgradeTML Civils85%
Fairwood Sewer ReplacementDitshimega30%
Homestead Sewer ReplacementMakhado90%
Jeppestown Sewer Replacement Phase 1Little Rocky63%
Jeppestown Sewer Replacement Phase 10Limontha60%
Jeppestown Sewer Replacement Phase 2Little Rocky63%
Jeppestown Sewer Replacement Phase 3Maletebogo Business Enterprise68%
Jeppestown Sewer Replacement Phase 4Ditshimega54%
Jeppestown Sewer Replacement Phase 5Isizwe Construction61%
Jeppestown Sewer Replacement Phase 6Seedi Developments26%
Jeppestown Sewer Replacement Phase 7Isizwe Construction86%
Jeppestown Sewer Replacement Phase 8Ditshimega85%
Jeppestown Sewer Replacement Phase 9Linomtha85%
Lorentzville Sewer Replacement Phase 1Maletebogo Business Enterprise72%
Lorentzville Sewer Replacement Phase 2Mavu Ashu Construction27%
Lorentzville Sewer Replacement Phase 3Mavu Ashu Construction30%
Strubensvalley Sewer Replacement Phase 2TML Civils95%
Protea Glen ext  29 Emergency Pipe ReplacementAbram Puno Harvest JV90%
Meadowlands Zone 8 Emergency Pipe ReplacementF & A Civils90%
Orange Farm ext 2 emergency W Pipe ReplacementAbram Puno Harvest JV85%
Meadowlands Zone 7 Emergency Pipe ReplacementAbram Puno Harvest JV85%
Lenasia ext 10 W Pipe ReplacementNandipha Projects cc90%
Blairgowrie Emergency Pipe ReplacementPlanet Earth100%
Weltevreden Park ext 1 Emergency pipe replacement (Water)DKPB Construction100%
Vandia Grove Ext 1 Emergency Pipe replacementMc Bee Trading90%
Rivonia Ext 1 Emergency Water Pipe ReplacementNandipha Projects CC25%
Constantia Kloof and Weltervreden Park Water Pipe ReplacementNandipha Projects CC85%
Mayfair Sewer ReplacementMaletebogo Business Enterprise100%
River Club Estate Emergency Water Pipe ReplacementF & A Civils0%
Melrose Estate Emergency Sewer Pipe ReplacementNJR Projects95%
 Ferndale Water Pipe ReplacementMotla Projects100%
 Alveda Sewer Rising Main DiversionPlanet Earth95%
Troyeville Sewer Replacement Phase 1Thalami Civils40%
Louis Botha Water ReplacementLilithalethu Trading 41
Troyeville Sewer Replacement Phase 2
Dam 01 -Construction of High Rate Settling tanks, pumping mains, Dam linerRaubex/ L&R JV
Lining of a dam at Driefontein WWTWEigenbau99%
Construction of a balancing tank at Bushkoppie WwTWUmzinyathi Construction cc99%
Upgrade of digester heating and mixing system at Olifantsvlei WWTW (MECHANICAL)WEC Projects (Pty) Ltd
Aeroton Tower 1.4 mlMurray & Dickson Motla Projects77%
Crown Garden Tower and Pump StationEsor Construction 70%
Construction of Swiss House FacilitiesAscension Properties Limited100%
Pressure ManagementLebaka Construction82%
PROTEA GLEN PUMP STATION King Civil Engineering99%
Lenasia Pump StationEIGENBAU (PTY) LTD/Dzeng JV97%
Ennerdale Phase 1Sihle Civil75%
Ennerdale Phase 2Mudzusi wa Vhutali75%
Lenasia Ext. 5 Phase 1Cool Action Trading100%
Lenasia Ext. 5 Phase 2Sakhile Projects cc100%
Lenasia Ext. 5 Phase 3Cool Action Trading100%
Lenasia Ext. 5 Phase 4Mavu-Ashu Civil Constructions cc100%
Lenasia Ext. 5 Phase 5Sakhile Projects cc100%
Lenasia Ext. 5 Phase 6Sakhile Projects cc100%
Provision of Basic Water in informal settlementsMotla Projects97%
STS Prepaid Meters Cosmo CitySakhikhaya Suppliers CC77%
Orange Farm 1AAnita65%
Orange Farm 2ALebaka70%
Orlando Pipe replacementMudzusi wa Vhutali90%
Soweto Infrastructure Upgrade DiepkloofBoxani Building and Civil72%
Paulshof Ext.1Iviwe Mosobotlhale JV90%
Bryanston Ext. 13Phumelela Dlomo Construction60%
Bryanston Ext. 34Adicon Investments (Pty) Ltd95%
Bryanston Mill HillBoxani Building And Civil Construction (Pty) Ltd90%
Eastgate Water pipe replacementWanga Power
Gallo Manor Phase 1Anita Building Construction (Pty) Ltd90%
Gallo Manor Phase 2A and P Civils and Trading (Pty) Ltd90%
Jukskei Ext. 1 Phase 1Cool Action Trading100%
Jukskei Ext. 1 Phase 2Abram Mashego Construction Puno Harvest JV100%
Klevehill ParkMavu-Ashu Civil Constructions cc75%
Ennerdale Water Upgrade Phase 2Bluestone Trench Technologies cc
Linbro EarthworksGabs Construction and Maintenance
Thalami Civils0.42
Troyeville Sewer Replacement Phase 3Selby Construction95%
Yeoville Sewer Pipe Replacement Phase 1Seedi Developments
Yeoville Sewer Pipe Replacement Phase 2Makhado Project Management
Thulani Hotspot RehabilitationThamandla Construction30%
Thulani Ward 129 Sewer Pipe replacementMakhado Project Management25%
Vukuphile Saxonwold E0%
Vukuphile Alan Manor F0%
Vukuphile JHB North C0%
Project nameContract numberPhysical Completion % Q3
NWWTW Unit 4 - liqourJW1359996%
Ennerdale WWTW: Infrastructure Renewal Plan - Module mixersJW1422699%
Unit 5 -Phase 2 (Civil works)JW13896RR70%
NWWTW IRP Phase 1 Electrical MV Upgrade and RefurbishmentJW1405499%
Randburg depot - Completion of the contruction of new Randburg DeptJW1426688%
Alternative Energy Project Phase 1JW1441296%
Erand Tower- Construction of New 2.0 Ml Tower and PumpstationJW13570RRRRR69%
Florida North pump stationJW13829RR99%
Kibler Park Sewer Pumpstation UpgradeJWOPS032/2280%
Refurbishment of Hector Norris Pump Station including pumps, VSDs, PLC and associated electrical worksJW1428765%
Pressure Management Phase 2B: Soweto PRVsJW1409695%
Pressure Management Phase 2A: Soweto PRVsJW1409585%
T-CODESOM2020_JW OPS 049/19R100%
Stretford Ext 6, 7 and 8 Sewer Bulk Pipe ReplacementJW14228B77%
Stretford Ext 7 Sewer Pipe Replacement Phase 2JW14228C70%
Stretford ext 4 Outfall SewerJW1429080%
Provision of basic water in CrosbyJW14416100%
Alexandra Renewal of Secondary Mains and Discretisation in Sub Block CUFW913_BLK C100%
Alexandra Renewal of Secondary Mains and Discretisation in Sub Block DUFW913_BLK D100%
Orange Farm 2BJW13858100%
Anthea Nancefield outfall SewerJW13575 RRR64%
Blairgowrie Water Pipe Replcament Phase 1JW14220H100%
Construction of a 26ML Concrete Reservoir and a 2ML Water Tower in Brixton with
associated pipe and pump works
JW1432290%
Protea South Ext 9 Sewer Pipe Replacement Phase 9JW14376100%
Sewer Pipe Replacement Louis Botha 3JW1423199%
Sewer Pipe Replacement Louis Botha 1JW14229100%
Parkwood Phase 3 Sewer Pipe ReplacementJW14228A92%
Cedar Lakes Sewer Pipe ReplacementJW14377100%
Sharonlea Water Pipe Replacement Phase 2JW14220B100%
Sharonlea Water Pipe Replacement Phase 1JW14220A100%
STS Meters Supply and technical supportJW14329_C100%
STS Meters Supply and technical supportJW14329_A100%
STS Meters Supply and technical supportJW14329_B100%
Supply and intsallation of STS water meters in cosmo city Phase 2JW1433531%
Project nameService ProviderContract numberPhysical Completion % Q3
NWWTW Unit 4 - liqourJW1359996%
Unit 5 -Phase 2 (Civil works)JW13896RR70%
Randburg depot - Completion of the contruction of new Randburg DeptJW1426688%
Woodmead Reservoir JW14289TBC
Erand Tower- Construction of New 2.0 Ml Tower and PumpstationJW13570RRRRR69%
Construction of a 26ML Concrete Reservoir and a 2ML Water Tower in Brixton with
associated pipe and pump works
JW1432290%
Florida North pump stationJW13829RR99%
Kibler Park Sewer Pumpstation UpgradeJWOPS032/2280%
Refurbishment of Hector Norris Pump Station including pumps, VSDs, PLC and associated electrical worksJW1428765%
Pressure Management Phase 2B: Soweto PRVsJW1409695%
Pressure Management Phase 2A: Soweto PRVsJW1409585%
Stretford Ext 6, 7 and 8 Sewer Bulk Pipe ReplacementJW14228B77%
Stretford Ext 7 Sewer Pipe Replacement Phase 2JW14228C70%
Stretford ext 4 Outfall SewerJW1429080%
Basic Sanitation - Naledi( 55% Capex)JW1446915%
Basic Sanitation - Poortjie Marikana( 10% Capex)JW1447041%
Basic Sanitation - Wilgespruit( 62% Capex)JW144720%
Anthea Nancefield outfall SewerJW13575 RRR64%
Halfway House Water UpgradeJW143240%
Diepsloot Sewer BridgesJW13518RRTBC
Sewer Pipe Replacement Louis Botha 3JW1423199%
Parkwood Phase 3 Sewer Pipe ReplacementJW14228A92%
Inchanga Sewer Rising MainJW144603%
Bezuidenhout Valley Phase 2 Sewer PipeJW14228E5%
Bezuidenhout Valley Phase 3 Sewer PipeJW14228F5%
Bezuidenhout Valley Phase 4 Sewer PipeJW14228D0%
Sharonlea Water Pipe Replacement Phase 3JW14220C90%
Inner Extreme Emergency SewerJW14228H0%
Deep South Extreme Emrgency SewerJW14228 G0%
STS Meters Supply and technical supportJW14329_C95%
Ennerdale WWTW: Infrastructure Renewal Plan - Module mixersJW1422699%
Alternative Energy Project Phase 1JW1441296%
Supply and installation of STS water meters in cosmo city Phase 2JW1433531%
T-CODESOM2020_JW OPS 049/19R100%
Protea South Ext 9 Sewer Pipe Replacement Phase 9JW14376100%
Cedar Lakes Sewer Pipe ReplacementJW14377100%
Alexandra Renewal of Secondary Mains and Discretisation in Sub Block CUFW913_BLK C100%
#Contract numberProject namePhysical Completion % Q3
25JW14228FBezuidenhout Valley Phase 3 Sewer Pipe5%
26JW14228DBezuidenhout Valley Phase 4 Sewer Pipe0%
27JW14220CSharonlea Water Pipe Replacement Phase 390%
28JW14228HInner Extreme Emergency Sewer0%
29JW14228 GDeep South Extreme Emrgency Sewer0%
30JW14329_CSTS Meters Supply and technical support95%
31JW14226Ennerdale WWTW: Infrastructure Renewal Plan - Module mixers99%
32JW14412Alternative Energy Project Phase 196%
33JW14335Supply and installation of STS water meters in cosmo city Phase 231%
Project NumberContract numberProject namePhysical Completion % Q4
UR1327JW14322Construction of a 26ML Concrete Reservoir and a 2ML Water Tower in Brixton with
associated pipe and pump works
90%
EI1303JW14289Woodmead Reservoir N/A