29 July 2024
Media Statement
Phase three of Rand Water Palmiet Pump Station maintenance is underway
The third phase, and the last of three, of the maintenance at Rand Water’s Palmiet Pump Station began today, Monday 29 July, at 05:00, and is scheduled to end on Tuesday, 30 July 2024 at 21:00.
During this time, pumping will be reduced to 76% for 40 hours, which means that 24% of Palmiet’s pumping capacity will be out of production.
Areas that are fed from the direct feeds, South Hills Tower, Alexander Park Reservoir, as well as the Linksfield Reservoir will be affected immediately when the maintenance begins; while areas that are supplied by the Sandton and Midrand reservoirs and towers will be affected gradually as all the reservoirs’ capacity gets depleted.
The following Johannesburg Water systems will be impacted during the maintenance period: all Sandton and Midrand systems, the South Hills Tower, as well as the Alexandra Park, Randjieslaagte, and Linksfield reservoirs.
Full recovery of the systems will take several days after maintenance has been completed. However, the areas supplied by the Sandton and Midrand reservoirs and towers may take longer to recover because the reservoirs need to first build capacity after being empty.
Johannesburg Water will make arrangements for alternative water supply at strategic points within the residential areas. However, residents are encouraged to store water in preparation for the maintenance.
Ends
Issued by: Johannesburg Water Communication and Marketing.